European Oil, Gas, and Renewable Energy Solutions >  News  

 Press Releases/Archive   |  Events Calendar 

..
> Homepage (News on Homepage)
> Upstream News
> Midstream News
> Downstream News
> Renewable Energy / Offshore Wind
> General Interest News 


 
. It takes great precision to move such a huge construction onto the barge - Photo  © Bladt

 

 

RWE Innogy: 'Wedding' on the high seas


Substation erected for the Nordsee Ost offshore wind farm in the German North Sea
1,800 ton substation platform successfully placed on foundation
The system will now be connected with the export cables and the inter-array cables,
prior to commissioning

Substation platform was successfully placed on foundation



July 21, 2014  + + +  A 'wedding' was celebrated on the Nordsee Ost offshore wind farm construction site of RWE Innogy: This is what the construction process is called when the foundation is successfully married to the substation platform. As a result the sea-based transformer substation and all its electrical components have now been successfully completed. (Photo © RWE)

The journey of the 1,800 ton substation started in Danish Aalborg and took three days to ship across the North Sea. The substation is 15 meters above the construction area of RWE Innogy’s Nordsee Ost offshore wind farm, which is located some 30 kilometres north of the island of Heligoland. A floating crane placed the heavyweight substation onto the foundation on Saturday, completing the installation of the heaviest component of the offshore wind farm.

“The substation was developed and built within a 16 month time frame by our contractor Bladt Industries, a steel construction company, together with the Danish subcontractors Semco and ISC,” said Matthias Esken, Project Manager for the transformer substation at Nordsee Ost. “We are now going to connect the substation with the previously installed inner-array cables and the TenneT export cables which remain to be installed.” And Marcel Sunier, Project Director for the Nordsee Ost wind farm at RWE Innogy, added: “The heart of the wind farm has now been installed with the transformer substation. As soon as access to the grid has been provided, we will start the commissioning. The wind farm is expected to be complete at the end of 2014, with the testing phase to be finished in spring 2015.”

The offshore substation transforms the electricity generated by the 48 wind turbines at 33 kV (kilo volt) to a transmission voltage of 155 kV. Submarine high-voltage cables then transmit the electricity to the transformer platform of TenneT where the AC voltage is transformed to 250 kV DC voltage and transmitted to the nearest grid access point at Brunsbüttel. The grid operator TenneT is responsible for the grid access.

Like the wind turbines, the transformer substation was anchored on a jacket foundation to the seabed and will rise about 40 meters above the sea level following final assembly.

Once complete, the Nordsee Ost offshore wind farm will have an installed capacity of some 295 megawatts and supply the equivalent of about 300,000 private households with electricity per year. Equipped with the currently most powerful offshore turbines, Nordsee Ost ranks among the largest commercial wind power projects off the German coast.

Source: RWE Innogy

+  +  + 

Bladt Industries:  Load out of the Nordsee Ost substation


July 7, 2014   + + +  Last week marked the end of yet another successful project at Bladt Industries, as the Bladt team completed the load out of the Nordsee Ost substation.

The substation is now on the barge, where it will undergo measures to secure sea fastening before it makes its journey to the final destination in the German North Sea. The 1900 tonnes substation, which Bladt Industries fabricated for the German utility company RWE, is the 13th substation fabricated by Bladt Industries.

The cooperation between RWE and Bladt has been great from day one. Both parties entered into the project with the same goal: to make a substation of the highest quality within a very strict time frame. The EPC-contract was completed within 15 months – quite a short time period to fabricate a substation.

Senior Project Manager, Torben Hother Hansen: “In this project we especially had one challenge – the time frame. However, with our knowledge and experience from previous projects we were able to reach our goals of fabricating a substation of the highest quality within a very tight time schedule.”

Source: Bladt Industries - www.bladt.dk

 



 








 










 








 




 

 






Worldwide more than
90,000 paid subscriptions

Worldwide more than 48,000 subscriptions -
100% one-year direct request qualification


'What's New' in Upstream, Midstream and Downstream Products & Services. Circulation 37,000

 
PennWell
Petroleum Group:

Oil & Gas Journal
Oil & Gas Journal Russia
OGJ_eNewsletter
 
OGJ-Website-Statistics

Oil, Gas & Petrochem Equipment

Offshore Magazine
Offshore Russia
Offshore eNewsletter 
Offshore Website Statistics

Oil & Gas Financial Journal

+ + + 

 For more information, media kits or sample copies please contact
Andreas Sicking
+49 (0)2903-338570

wilhelms@pennwell.com www.sicking.de


Please send news releases to Wilhelm Sicking - sicking-media@email.de