European Oil, Gas, and Renewable Energy Solutions >  News  

 Press Releases/Archive   |  Events Calendar 

..
> Homepage (News on Homepage)
> Upstream News
> Midstream News
> Downstream News
> Renewable Energy / Offshore Wind
> General Interest News 


 
. Saipem Castoro Sei (© Saipem)

 



South Stream Transport
awards contracts for line pipe supply of the Second Offshore Pipeline
Saipem Contracted for the Construction of the South Stream Offshore Pipeline


Marubeni-Itochu & Sumitomo Consortium, OMK Steel and Izhora Pipe Mill
to supply pipes for the second line of the South Stream Offshore Pipeline
Total contract value of approximately 800 million euros


March 14, 2014 + + + South Stream Transport has ordered over 75,000 pipes for second line of the South Stream Offshore Pipeline, with a total order value of about 800 million euros. Marubeni-Itochu & Sumitomo Consortium from Japan will supply 40% of the pipes, OMK Steel from Russia 35%, and Izhora Pipe Mill from Russia another 25%.

Dr. Oleg Aksyutin, CEO of South Stream Transport, and Vladimir Markin, CEO of OMK
Dr. Oleg Aksyutin, CEO of South Stream Transport, and Vitaly Motorin, General Manager of Severstal Izhora pipe mill


The South Stream Offshore Pipeline will be made up of four parallel pipelines of 931 kilometres each. Each pipeline is constructed of over 75,000 pipes of 12 metres each. Pipe-supply contracts for the first line were signed in January 2014 with producers in Germany (Europipe) and Russia. Following delivery and stockpiling of pipes at the Black Sea coast, offshore construction will start in autumn 2014. The first offshore pipeline is scheduled to start operations by the end of 2015.

 

+ + +



Saipem Contracted for the Construction of the South Stream Offshore Pipeline
Total contracts value of approximately 2 billion Euros

Saipem to construct the first line, shore crossings and associated facilities
for all four pipelines

March 14, 2014 + + + South Stream Transport has contracted the Italian company Saipem for the construction of the South Stream Offshore Pipeline. Oleg Aksyutin, CEO of South Stream Transport B.V. and Stefano Bianchi, SVP of Saipem S.p.A signed the contracts in Amsterdam today.

The South Stream Offshore Pipeline will consist of four parallel gas pipelines each 931 kilometres long across the Black Sea, from Russia to Bulgaria. Each pipeline will be made up of over 75,000 individual pipes which are welded together on-board special pipe-laying vessels and then laid at depths of up to 2,200 metres. The agreements with Saipem cover the design and construction of line 1 and construction of the shallow water parts,, shore crossings, landfall and associated facilities for all four pipelines.

Two vessels involved in pipeline construction

The South Stream Offshore Pipeline will be laid by several pipe-laying vessels of Saipem: Saipem’s Castoro Sei, a S-lay vessel suitable for both shallow and deep waters ... and  Saipem 7000, a J-Lay vessel suitable for ultra-deep water that had already constructed the Blue Stream pipeline in the Black Sea.
Saipem Castoro Sei (© Saipem) Saipem S7000 (© Saipem)

For the shore crossings, four micro-tunnels will be constructed on both the Russian and the Bulgarian side, each with a length of over 1 kilometre. These tunnels allow construction of the pipeline without significant construction works at the surface of the beach and shallow waters, thereby preserving the integrity of Russian and Bulgarian shores and mitigating environmental impact.

Construction to start in June 2014

Activities at the landfalls will commence in June of 2014 with the preparations for micro-tunnel construction in both Russia and then in Bulgaria.

Offshore construction will start in autumn 2014. In September 2014, the first pipes will be welded together in batches of 4 on-board the Castoro Sei to form so-called quad-joints of 48 metres long. In November 2014, the Castoro Sei vessel will move to Russian waters to start offshore pipe-laying. At the end of the year, the larger pipelay vessel S7000 will take over pipe laying and the Castoro Sei will move back to the Bulgarian harbour to continue quad-joint welding.

On board the S7000, the 48-metre quad-joint pipes will be placed vertically in a large tower (J-lay tower) and welded to the main string before being lowered onto the seabed. This method is referred to as J-lay, referring to the shape of the pipeline as it is lowered on the seabed.

Construction of the first pipeline is to last until the third quarter of 2015, so the completed Russia to Bulgaria pipeline will be taken into operations phase by the end of that year.

Source: South Stream Transport
media@south-stream-transport.com
www.south-stream-offshore.com







Worldwide more than
100,000 paid subscriptions

Worldwide more than 48,000 subscriptions -
100% one-year direct request qualification


'What's New' in Upstream, Midstream and Downstream Products & Services


PennWell
Petroleum Group:

Oil & Gas Journal
Oil & Gas Journal Russia
OGJ LatinoAmericana
OGJ_eNewsletter
 
OGJ-Website-Statistics

Oil, Gas & Petrochem Equipment

Offshore Magazine
Offshore Russia
Offshore eNewsletter 
Offshore Website Statistics

Oil & Gas Financial Journal

+ + + 

 For more information, media kits or sample copies please contact
Andreas Sicking
+49 (0)2903-338570

wilhelms@pennwell.com www.sicking.de


Please send news releases to Wilhelm Sicking - sicking-media@email.de